§ 107-10. Timing of impact fee assessment and payment.  


Latest version.
  • (a)

    Development impact fees shall be assessed at the time of application for a building permit and collected in accordance with the requirements of this section.

    (b)

    All development impact fees shall be collected no earlier than at the time of issuance of a building permit, or with the administrator's approval no later than as a prerequisite to issuance of an interior finishes permit or a certificate of occupancy for the building or building shell.

    (c)

    For projects not involving issuance of a building permit, all development impact fees shall be collected at the time of approval of the development permit or such other authorization to commence construction or to commence use of a property, whichever is earliest.

    (d)

    If the final use of a building cannot be determined at the time of the initial building permit, the administrator shall have the authority to assess a development impact fee based on the most likely use of the building, and shall adjust the fee in accordance with the following:

    (1)

    Prior to the completion of the project, and as a condition to the issuance of an interior finishes permit or a certificate of occupancy, as applicable, the developer shall recertify in writing to the administrator the actual land use or uses of the project, and shall present an architect's certificate of the actual gross square footage of floor area attributable to each use.

    (2)

    In the event that the actual land use or uses and/or the actual gross square footage applicable to the actual land use or uses differs from that originally certified, and in the event that the impact fee applicable to the actual land use or uses and/or gross square footage exceeds the impact fee previously paid, the developer shall be required to pay the amount of the excess as a condition to the issuance of an interior finishes permit or a certificate of occupancy.

    (3)

    The amount of the excess shall be based upon the impact fee schedule in effect on the date the interior finishes permit or the certificate of occupancy is issued.

    (4)

    If the actual gross square footage constructed after the issuance of the building permit is less than the amount originally certified, the developer shall be entitled to a refund of the excess portion of the fee in accordance with this chapter.

    (e)

    Change of use, redevelopment, expansion or modification.

    (1)

    Any future change in demand for public facilities in excess of the average demand anticipated at the time of issuance of the original building permit shall result in the assessment of such additional fee, net of the previous fee paid, as would otherwise have been due.

    (2)

    Future changes in demand may result from a change in the land use category of the occupant of the building or property, the expansion of a building or use on a property that results in an increase in the units of development (as defined herein), or the subsequent discovery of facts unknown or misrepresented at the time of issuance of the original building permit.

( Ord. No. 2016-10-33 , § I, 10-18-2016)